Gulf Coast · 2027

2027 Gulf Coast Turnaround Calendar

PBF and CITGO have moved planned work at Chalmette and Lake Charles into 2027. Trade reports also point to a Beaumont overhaul extending from December 2026 into January 2027 and a fall 2027 turnaround at Motiva Port Arthur. Those four are the sourced refinery turnaround windows.

The calendar now also carries six projected cycle candidates built from each facility's last documented turnaround, routine maintenance at Cheniere's two LNG facilities, the proposed restart of the former LyondellBasell Houston refinery, and three project watch records. Every entry identifies its evidence and how precisely the timing is known; a projection is a planning estimate, not an announced schedule.

Source: PBF Energy / SEC; CITGO press release, distributed by PR Newswire; Reuters, republished by EnergyNow; MNI, citing Bloomberg reporting; Cheniere management statements, transcribed by MarketBeat; Valero / SEC

Sources last reviewed: .

A confirmed year does not mean that start and finish dates have been announced.

16 entries: 4 sourced refinery turnarounds, 6 projected cycle candidates, 2 LNG maintenance outlooks, 1 restart project and 3 project watch records.

Entries marked Projected are cycle estimates built from a facility’s last documented turnaround. They have no announced schedule and exist so suppliers can prequalify and watch the operator’s next disclosure. Show only projections or only confirmed entries.

Beaumont, TX Turnaround

ExxonMobil Beaumont

Reuters reports FCC and hydrotreater work beginning in December 2026 and continuing into January 2027. ExxonMobil has not confirmed the operational details.

Reported

December 2026 into January 2027

Sources last reviewed: Nov 6, 2026

View details

Chalmette, LA Turnaround

PBF Chalmette

PBF has deferred the Chalmette turnaround from the fourth quarter of 2026 to 2027. The original plan covered the crude unit and coker; the revised execution window is not disclosed.

Confirmed

2027; month and quarter not disclosed

Sources last reviewed: Oct 31, 2026

View details

Lake Charles, LA Turnaround

CITGO Lake Charles

CITGO has moved the Lake Charles coker turnaround into 2027. Its results announcement does not specify a quarter, start date or duration.

Confirmed

2027; quarter and dates not disclosed

Sources last reviewed: Oct 31, 2026

View details

Port Arthur, TX Turnaround

Motiva Port Arthur

MNI, citing Bloomberg, reports that Motiva has deferred its VPS-5 crude-unit turnaround and associated naphtha-processing work to fall 2027.

Reported

Fall 2027; exact dates not disclosed

Sources last reviewed: Nov 6, 2026

View details

Cameron Parish, LA Routine maintenance

Sabine Pass LNG

Cheniere’s outlook includes routine maintenance at Sabine Pass. Management says no long-duration major turnaround is planned for 2027; site-specific dates are not disclosed.

Reported

2027 routine maintenance; site-specific dates not disclosed

Sources last reviewed: Oct 31, 2026

View details

San Patricio County, TX Routine maintenance

Corpus Christi LNG

Corpus Christi is included in Cheniere’s 2027 routine-maintenance outlook. The cited management statement identifies no specific train, shutdown date or long-duration major turnaround.

Reported

2027 routine maintenance; site-specific dates not disclosed

Sources last reviewed: Oct 31, 2026

View details

Houston, TX Restart project

Former LyondellBasell Houston refinery

Valero has announced an agreement to acquire the former LyondellBasell Houston refinery and targets a 165,000-barrel-per-day restart by year-end 2027. Closing remains subject to conditions.

Confirmed

Restart target: by year-end 2027

Sources last reviewed: Oct 31, 2026

View details

Corpus Christi, TX Turnaround

Valero Corpus Christi West

The West complex's 2022 conversion-unit turnarounds place a five-year cycle in 2027. Valero has not disclosed a schedule; this is a projection.

Projected

2027 cycle candidate; no disclosed window

Sources last reviewed: Nov 6, 2026

View details

Garyville, LA Turnaround

Marathon Garyville

Garyville's 2019 and 2022 crude train work and the 2022 FCCU block put a five-year cycle near 2027, but Marathon calls 2027 a lighter turnaround year. Watch item only.

Projected

2027 cycle candidate; no disclosed window

Sources last reviewed: Nov 6, 2026

View details

Baytown, TX Turnaround

ExxonMobil Baytown

Baytown's January pattern in 2022, 2023 and 2026 makes early 2027 a candidate for the conversion units not covered by the 2026 crude work. ExxonMobil has not disclosed a schedule.

Projected

2027 cycle candidate; no disclosed window

Sources last reviewed: Nov 6, 2026

View details

Baton Rouge, LA Turnaround

ExxonMobil Baton Rouge

Baton Rouge's 2022 FCC work returns on a four to five year cycle in 2026 or 2027, alongside crude units not covered in 2023 and 2024. ExxonMobil has not disclosed a schedule.

Projected

2027 cycle candidate; no disclosed window

Sources last reviewed: Nov 6, 2026

View details

Westlake, LA Turnaround

Phillips 66 Lake Charles

Lake Charles's 2022 crude and reformer work on a five-year cycle and the end-2027 steam turbine project both point at 2027. Phillips 66 has not disclosed a schedule.

Projected

2027 cycle candidate; no disclosed window

Sources last reviewed: Nov 6, 2026

View details

Port Arthur, TX Turnaround

Valero Port Arthur

Port Arthur's January blocks in 2022, 2023 and 2024 put the 2022 conversion units on a five-year cycle in 2027. Valero has not disclosed a schedule; the 2026 hydrotreater rebuild may shift sequencing.

Projected

2027 cycle candidate; no disclosed window

Sources last reviewed: Nov 6, 2026

View details

Pascagoula, MS Project watch

Chevron Pascagoula

Chevron confirmed a large fourth-quarter 2026 Pascagoula turnaround and two more cycles before 2030. Whether the work runs into January 2027 is not disclosed.

Reported

Fourth-quarter 2026 turnaround under way; 2027 carryover not stated

Sources last reviewed: Nov 6, 2026

View details

Texas City, TX Project watch

Marathon Galveston Bay and Garyville

Marathon's Galveston Bay distillate hydrotreater and Garyville feedstock projects are expected in service by year-end 2027. Capital projects, not turnarounds; tie-in outages are not stated.

Confirmed

In service by year-end 2027

Sources last reviewed: Nov 6, 2026

View details

Sabine Pass, TX Project watch

Gulf Coast LNG in 2027

Golden Pass Train 2 and Plaquemines Phase 2 are expected to start in 2027. These are commissioning milestones; no major Gulf Coast LNG turnaround has been disclosed for 2027.

Reported

Golden Pass Train 2 first half 2027; Plaquemines Phase 2 mid 2027

Sources last reviewed: Nov 6, 2026

View details

Plan your account outreach

Use the calendar to identify facilities to follow, then research relevant company and facility contacts in ExecGraph.

Sources
PBF Energy third-quarter 2026 release

PBF Energy / SEC · Published 2026-10-29

CITGO second-quarter 2026 results

CITGO press release, distributed by PR Newswire · Published 2026-08-13

Exxon plans spring and year-end Beaumont overhauls

Reuters, republished by EnergyNow · Published 2026-04-08

Motiva Port Arthur delays fall work on largest CDU by a year

MNI, citing Bloomberg reporting · Published 2026-05-22

Cheniere third-quarter 2026 earnings call transcript

Cheniere management statements, transcribed by MarketBeat · Published 2026-10-29

Valero to acquire former Houston refinery from LyondellBasell

Valero / SEC · Published 2026-10-30