Beaumont, TX Turnaround
ExxonMobil Beaumont
Reuters reports FCC and hydrotreater work beginning in December 2026 and continuing into January 2027. ExxonMobil has not confirmed the operational details.
Gulf Coast · 2027
PBF and CITGO have moved planned work at Chalmette and Lake Charles into 2027. Trade reports also point to a Beaumont overhaul extending from December 2026 into January 2027 and a fall 2027 turnaround at Motiva Port Arthur. Those four are the sourced refinery turnaround windows.
The calendar now also carries six projected cycle candidates built from each facility's last documented turnaround, routine maintenance at Cheniere's two LNG facilities, the proposed restart of the former LyondellBasell Houston refinery, and three project watch records. Every entry identifies its evidence and how precisely the timing is known; a projection is a planning estimate, not an announced schedule.
Source: PBF Energy / SEC; CITGO press release, distributed by PR Newswire; Reuters, republished by EnergyNow; MNI, citing Bloomberg reporting; Cheniere management statements, transcribed by MarketBeat; Valero / SECSources last reviewed: .
A confirmed year does not mean that start and finish dates have been announced.
16 entries: 4 sourced refinery turnarounds, 6 projected cycle candidates, 2 LNG maintenance outlooks, 1 restart project and 3 project watch records.
Entries marked Projected are cycle estimates built from a facility’s last documented turnaround. They have no announced schedule and exist so suppliers can prequalify and watch the operator’s next disclosure. Show only projections or only confirmed entries.
16 of 16 entries
Beaumont, TX Turnaround
Reuters reports FCC and hydrotreater work beginning in December 2026 and continuing into January 2027. ExxonMobil has not confirmed the operational details.
Chalmette, LA Turnaround
PBF has deferred the Chalmette turnaround from the fourth quarter of 2026 to 2027. The original plan covered the crude unit and coker; the revised execution window is not disclosed.
Lake Charles, LA Turnaround
CITGO has moved the Lake Charles coker turnaround into 2027. Its results announcement does not specify a quarter, start date or duration.
Port Arthur, TX Turnaround
MNI, citing Bloomberg, reports that Motiva has deferred its VPS-5 crude-unit turnaround and associated naphtha-processing work to fall 2027.
Cameron Parish, LA Routine maintenance
Cheniere’s outlook includes routine maintenance at Sabine Pass. Management says no long-duration major turnaround is planned for 2027; site-specific dates are not disclosed.
2027 routine maintenance; site-specific dates not disclosed
Sources last reviewed: Oct 31, 2026
View detailsSan Patricio County, TX Routine maintenance
Corpus Christi is included in Cheniere’s 2027 routine-maintenance outlook. The cited management statement identifies no specific train, shutdown date or long-duration major turnaround.
2027 routine maintenance; site-specific dates not disclosed
Sources last reviewed: Oct 31, 2026
View detailsHouston, TX Restart project
Valero has announced an agreement to acquire the former LyondellBasell Houston refinery and targets a 165,000-barrel-per-day restart by year-end 2027. Closing remains subject to conditions.
Corpus Christi, TX Turnaround
The West complex's 2022 conversion-unit turnarounds place a five-year cycle in 2027. Valero has not disclosed a schedule; this is a projection.
Garyville, LA Turnaround
Garyville's 2019 and 2022 crude train work and the 2022 FCCU block put a five-year cycle near 2027, but Marathon calls 2027 a lighter turnaround year. Watch item only.
Baytown, TX Turnaround
Baytown's January pattern in 2022, 2023 and 2026 makes early 2027 a candidate for the conversion units not covered by the 2026 crude work. ExxonMobil has not disclosed a schedule.
Baton Rouge, LA Turnaround
Baton Rouge's 2022 FCC work returns on a four to five year cycle in 2026 or 2027, alongside crude units not covered in 2023 and 2024. ExxonMobil has not disclosed a schedule.
Westlake, LA Turnaround
Lake Charles's 2022 crude and reformer work on a five-year cycle and the end-2027 steam turbine project both point at 2027. Phillips 66 has not disclosed a schedule.
Port Arthur, TX Turnaround
Port Arthur's January blocks in 2022, 2023 and 2024 put the 2022 conversion units on a five-year cycle in 2027. Valero has not disclosed a schedule; the 2026 hydrotreater rebuild may shift sequencing.
Pascagoula, MS Project watch
Chevron confirmed a large fourth-quarter 2026 Pascagoula turnaround and two more cycles before 2030. Whether the work runs into January 2027 is not disclosed.
Fourth-quarter 2026 turnaround under way; 2027 carryover not stated
Sources last reviewed: Nov 6, 2026
View detailsTexas City, TX Project watch
Marathon's Galveston Bay distillate hydrotreater and Garyville feedstock projects are expected in service by year-end 2027. Capital projects, not turnarounds; tie-in outages are not stated.
Sabine Pass, TX Project watch
Golden Pass Train 2 and Plaquemines Phase 2 are expected to start in 2027. These are commissioning milestones; no major Gulf Coast LNG turnaround has been disclosed for 2027.
Golden Pass Train 2 first half 2027; Plaquemines Phase 2 mid 2027
Sources last reviewed: Nov 6, 2026
View detailsUse the calendar to identify facilities to follow, then research relevant company and facility contacts in ExecGraph.
PBF Energy / SEC · Published 2026-10-29
CITGO press release, distributed by PR Newswire · Published 2026-08-13
Reuters, republished by EnergyNow · Published 2026-04-08
MNI, citing Bloomberg reporting · Published 2026-05-22
Cheniere management statements, transcribed by MarketBeat · Published 2026-10-29
Valero / SEC · Published 2026-10-30