Historical Gulf Coast turnarounds and prior plans

These four examples provide context for the 2027 calendar. They include historical maintenance plans, a deferred turnaround and a contractor’s account of site support. Each is identified by the kind of evidence it provides; a planned duration is not an actual completion record.

Sources last reviewed: .

Motiva Port Arthur: the September 2019 VPS-5 plan

Industrial Info Resources reported plans for 60 days of work on VPS-5 and 45 days on the associated naphtha hydrotreater, reformer and isomerization unit.

This is a relevant comparison because the same general group of units appears in the reported fall 2027 scope. It does not establish the duration of the 2027 turnaround.

Source: Industrial Info Resources; MNI, citing Bloomberg reporting

PBF Chalmette: the deferred fourth-quarter 2026 plan

OPIS reported crude-unit and coker work with a planned duration of 50 to 55 days. PBF subsequently moved the turnaround into 2027.

This is the earlier plan for the same work, not evidence of a completed 2026 outage. The original duration has not been reconfirmed for 2027.

Source: OPIS / Dow Jones; PBF Energy / SEC

ExxonMobil Baton Rouge: the 2022 FCC plan

Reuters reported an FCC shutdown beginning February 25, 2022, an original seven-week plan and a later April 5 completion target.

The example offers context for FCC maintenance at another refinery. Neither the original plan nor the later target establishes actual completion, and neither sets Beaumont’s 2026–2027 schedule.

Source: Reuters, republished by Euronews

Pascagoula: turnaround support in January 2022

In a contractor account published in 2024, Sodexo describes 11 weeks of around-the-clock support for the January 2022 turnaround, with as many as 4,800 additional contractors.

The account illustrates the scale of site support during that event. It is not a staffing forecast for CITGO Lake Charles or another 2027 turnaround.

Source: Sodexo

This is a selected set of comparisons, not a complete history of Gulf Coast outages.

Sources
Motiva to begin turnaround at Port Arthur refinery

Industrial Info Resources · Published 2019-09-03

Motiva Port Arthur delays fall work on largest CDU by a year

MNI, citing Bloomberg reporting · Published 2026-05-22

PBF 2026 turnaround guidance

OPIS / Dow Jones · Published 2026-01-06

PBF Energy third-quarter 2026 release

PBF Energy / SEC · Published 2026-10-29

Exxon plans to finish Baton Rouge FCC work by April 5

Reuters, republished by Euronews · Published 2022-04-01