Historical Gulf Coast turnarounds and prior plans
These four examples provide context for the 2027 calendar. They include historical maintenance plans, a deferred turnaround and a contractor’s account of site support. Each is identified by the kind of evidence it provides; a planned duration is not an actual completion record.
Sources last reviewed: .
Motiva Port Arthur: the September 2019 VPS-5 plan
Industrial Info Resources reported plans for 60 days of work on VPS-5 and 45 days on the associated naphtha hydrotreater, reformer and isomerization unit.
This is a relevant comparison because the same general group of units appears in the reported fall 2027 scope. It does not establish the duration of the 2027 turnaround.
Source: Industrial Info Resources; MNI, citing Bloomberg reportingPBF Chalmette: the deferred fourth-quarter 2026 plan
OPIS reported crude-unit and coker work with a planned duration of 50 to 55 days. PBF subsequently moved the turnaround into 2027.
This is the earlier plan for the same work, not evidence of a completed 2026 outage. The original duration has not been reconfirmed for 2027.
Source: OPIS / Dow Jones; PBF Energy / SECExxonMobil Baton Rouge: the 2022 FCC plan
Reuters reported an FCC shutdown beginning February 25, 2022, an original seven-week plan and a later April 5 completion target.
The example offers context for FCC maintenance at another refinery. Neither the original plan nor the later target establishes actual completion, and neither sets Beaumont’s 2026 to 2027 schedule.
Source: Reuters, republished by EuronewsPascagoula: turnaround support in January 2022
In a contractor account published in 2024, Sodexo describes 11 weeks of around-the-clock support for the January 2022 turnaround, with as many as 4,800 additional contractors.
The account illustrates the scale of site support during that event. It is not a staffing forecast for CITGO Lake Charles or another 2027 turnaround.
Source: SodexoGaryville: crude train cadence, 2019 and 2022
Industrial Info reported both Crude 10 trains under planned maintenance from October 21, 2019 for six to eight weeks, with a stated five-year interval, and 21-day Crude 10 A and 10 B turnarounds from October 3, 2022.
The interval is Industrial Info's characterization. It supports a cycle projection and does not establish a 2027 date.
Source: Industrial Info Resources; Industrial Info ResourcesPascagoula: the 2022 FCCU and coker plans
Industrial Info reported a 45-day FCCU turnaround from January 9, 2022, three other units for 30 days, and a 47-day delayed coker turnaround moved up to March 2022.
These show recent cadence at the site. They do not establish the fourth-quarter 2026 scope Chevron has disclosed or any 2027 date.
Source: Industrial Info ResourcesDeer Park: the 2024 spring block and the 2025 Big Block
A staggered DU-1, hydrocracker, vacuum and sulfur unit turnaround ran from March 2024 to late May 2024, and a roughly 60-day DU-2 overhaul from early October 2025 took the FCCU, hydrocracker and coker down with it.
With both blocks recently worked, Deer Park is not projected as a 2027 cycle candidate.
Source: MNI Market News, citing Bloomberg; Reuters, republished by Pipeline and Gas JournalRecently completed blocks that are not 2027 candidates
TotalEnergies Port Arthur ran a 60-day small crude unit, vacuum, reformer and hydrotreater overhaul from August 2025. CITGO completed a major crude system turnaround at Corpus Christi in the fourth quarter of 2025. Shell ran the Norco RCCU, alkylation, naphtha hydrotreater and GO-1 turnaround from August 15, 2025. LyondellBasell ran a 60-day Channelview cracker, Flex-1 and C4 turnaround from February 2025.
On cycle grounds none of these sites is projected for 2027.
Source: Reuters, republished by BOE Report; CITGO press release, republished by MiningStockEducation; Hydrocarbon Processing, quoting a Shell spokesperson; Argus MediaGulf Coast crackers: cadence used in screening
Cedar Bayou's 1592 unit was down about 120 days from April 2022 and its 1594 unit 60 days from September 2023; Dow's Freeport LHC-7 turnaround restarted in November 2022; Westlake's Petro 1 ran from late January into April 2025.
Crackers commonly run five to six year cycles, which keeps the 2022 units as 2027 or 2028 watch items rather than projected 2027 events.
Source: Industrial Info Resources; Industrial Info Resources; Industrial Info ResourcesThis is a selected set of comparisons, not a complete history of Gulf Coast outages.
Sources
Industrial Info Resources · Published 2019-09-03
MNI, citing Bloomberg reporting · Published 2026-05-22
OPIS / Dow Jones · Published 2026-01-06
PBF Energy / SEC · Published 2026-10-29
Reuters, republished by Euronews · Published 2022-04-01
Sodexo · Published 2024-07-17
Industrial Info Resources · Published 2019-10-24
Industrial Info Resources · Published 2022-10-05
Industrial Info Resources · Published 2022-01-12
MNI Market News, citing Bloomberg · Published 2024-04-03
Reuters, republished by Pipeline and Gas Journal · Published 2025-08-15
Reuters, republished by BOE Report · Published 2025-08-19
CITGO press release, republished by MiningStockEducation · Published 2025-11-13
Hydrocarbon Processing, quoting a Shell spokesperson · Published 2025-08-15
Argus Media · Published 2025-04-25
Industrial Info Resources · Published 2022-04-07
Industrial Info Resources · Published 2023-09-07
Industrial Info Resources · Published 2022-10-13