PBF Chalmette: turnaround deferred to 2027
The 2027 deferral is confirmed; execution dates are not disclosed.
PBF Energy has moved its planned Chalmette turnaround from the fourth quarter of 2026 to 2027. The company’s October 29, 2026 results release confirms the deferral but does not specify an execution month or quarter.
Source: PBF Energy / SECSources last reviewed: .
Crude-unit and coker scope
OPIS reported that the original 2026 plan covered the crude unit and coker, with an expected duration of 50 to 55 days. That duration belongs to the earlier plan; it has not been reconfirmed for 2027.
Source: OPIS / Dow Jones; PBF Energy / SECHow the plan changed
The January 2026 reporting described work scheduled for the fourth quarter of that year. PBF’s later disclosure moved the turnaround into 2027.
The earlier plan remains useful background on the units involved. It is not a completed outage history or a substitute for a revised execution schedule.
Source: OPIS / Dow Jones; PBF Energy / SECServices to assess
These categories reflect the original scope. They are planning considerations, not announced work packages, contract awards or open bids.
- Mechanical services
- Tower and heat-exchanger work
- Inspection and nondestructive examination
- Scaffolding and insulation
- Turnaround logistics
Updates
PBF announced that the planned fourth-quarter 2026 turnaround would move to 2027.
Source: PBF Energy / SECInitial calendar entry incorporating the deferral and the original scope reported by OPIS.
Source: PBF Energy / SEC; OPIS / Dow JonesSources
PBF Energy / SEC · Published 2026-10-29
OPIS / Dow Jones · Published 2026-01-06