Motiva Port Arthur: fall 2027 turnaround

ReportedFall 2027; exact dates not disclosed

MNI, citing Bloomberg; not an operator-confirmed schedule.

Motiva’s largest crude-unit turnaround and associated naphtha-processing work at Port Arthur are reported to have moved from fall 2026 to fall 2027. A May 22, 2026 MNI report, citing Bloomberg, identifies the deferral.

Source: MNI, citing Bloomberg reporting

Sources last reviewed: .

View relevant contacts

VPS-5 and the naphtha-processing units

The reported scope includes the VPS-5 crude unit, naphtha hydrotreater, catalytic reformer and isomerization unit. The cited reporting establishes a fall 2027 window, not an exact start date or outage duration.

Source: MNI, citing Bloomberg reporting

What the 2019 plan tells us

Industrial Info Resources reported a September 2019 plan allowing 60 days for VPS-5 and 45 days for the associated naphtha hydrotreater, reformer and isomerization unit.

The same general group of units makes that plan a relevant comparison. Its planned durations should not be carried over as the 2027 schedule.

Source: Industrial Info Resources

Services to assess

These categories reflect the reported unit scope. They are planning considerations, not announced work packages, contract awards or open bids.

  • Tower and heat-exchanger work
  • Catalyst services
  • Rotating-equipment services
  • Electrical and instrumentation
  • Scaffolding and insulation
  • Site logistics

Updates

MNI reported the deferral of the crude-unit and naphtha-processing work from fall 2026 to fall 2027.

Source: MNI, citing Bloomberg reporting

Initial calendar entry incorporating the reported deferral and the 2019 comparison.

Source: MNI, citing Bloomberg reporting; Industrial Info Resources

A June 2026 Bloomberg report restated the deferral to fall 2027. It names no units and is a second report of the same deferral, not operator confirmation.

Source: Bloomberg News, republished by EnergyNow

Questions answered

When is the Motiva Port Arthur turnaround in 2027?

Fall 2027; exact dates not disclosed. The cited source supports a season, not a month or exact dates.

How is the Motiva Port Arthur 2027 entry classified, and what supports it?

Reported. MNI, citing Bloomberg; not an operator-confirmed schedule. The timing rests on MNI, citing Bloomberg reporting; every source is linked on this page with the date it was last reviewed (2026-11-06).

What work is involved at Motiva Port Arthur?

Reported scope includes VPS-5, the naphtha hydrotreater, catalytic reformer and isomerization unit. No exact start date or 2027 duration is established. Service categories that may be relevant: Tower and exchanger work; Catalyst services; Rotating-equipment services; Instrumentation and electrical; Scaffolding and insulation; Site logistics. These are planning considerations, not contract awards, procurement commitments or open bids.

Sources
Motiva Port Arthur delays fall work on largest CDU by a year

MNI, citing Bloomberg reporting · Published 2026-05-22

Motiva to begin turnaround at Port Arthur refinery

Industrial Info Resources · Published 2019-09-03

US crude refiners are pushing run rates to maximum levels

Bloomberg News, republished by EnergyNow · Published 2026-06-01