Marathon Garyville: 2027 cycle watch
Cycle watch item; Marathon describes 2027 as lighter.
Garyville's crude trains had planned maintenance in October 2019 and October 2022, and the FCCU and alkylation block had eight weeks of work in the fall of 2022. Marathon said on November 3, 2026 that 2027 would be a lighter turnaround year than 2026 and named no facility. This entry is a watch item, not a reported plan.
Source: Industrial Info Resources; Industrial Info Resources; The Motley Fool transcript of Marathon managementSources last reviewed: .
The 2019 and 2022 work this projection rests on
Industrial Info reported both Crude 10 trains, Delayed Coker 205 and Platformer 12 under planned maintenance from October 21, 2019 for six to eight weeks, and said the full unit was not expected to be taken fully down again for five years.
In October 2022 Industrial Info reported 21-day Crude 10 A and 10 B turnarounds and eight weeks of planned maintenance on FCCU 25, HF Alkylation 27 and Gasoline Desulfurizer 55.
Source: Industrial Info Resources; Industrial Info ResourcesWhat Marathon has said
Marathon management said 2027 looks like a lighter turnaround year than 2026 and that no 2026 turnarounds were deferred. The company's third-quarter release lists Garyville feedstock projects expected in service by year-end 2027; it does not say whether tie-in requires an outage.
Together these cut against a large Garyville event in 2027 without ruling out conversion-unit work.
Source: The Motley Fool transcript of Marathon management; Marathon Petroleum / SECWhat a projection means here
A projected entry is a planning estimate built from the facility's last documented turnaround and a typical unit cycle. It is not an announced schedule, and the operator has not confirmed any 2027 work at this site.
Use it to decide where to prequalify and whose next quarterly disclosure to watch. Do not use it to time mobilization or to represent a schedule to a customer.
Services to assess
These categories reflect the candidate scope. They are planning considerations, not announced work packages, contract awards or open bids.
- Mechanical services
- Tower and heat-exchanger work
- Catalyst handling
- Inspection and NDE
- Scaffolding and insulation
- Turnaround logistics
Updates
Initial cycle projection from the documented 2019 and 2022 Garyville turnarounds, tempered by Marathon's statement that 2027 is a lighter turnaround year.
Source: Industrial Info Resources; Industrial Info Resources; The Motley Fool transcript of Marathon managementSources
Industrial Info Resources · Published 2022-10-05
Industrial Info Resources · Published 2019-10-24
The Motley Fool transcript of Marathon management · Published 2026-11-03
Marathon Petroleum / SEC · Published 2026-11-03