Baton Rouge has documented turnarounds in each of 2022, 2023 and 2024. On a four to five year cycle the FCC and hydrotreater worked in early 2022 return in 2026 or 2027. ExxonMobil has not disclosed any 2027 Baton Rouge maintenance. This entry is a projection.

Source: Reuters, republished by BOE Report; Industrial Info Resources; Reuters, republished by Euronews

Sources last reviewed: .

The recent work this projection rests on

Reuters reported the PCLA 3 FCC shut February 25, 2022 for a seven-week overhaul with a diesel hydrotreater to follow. Industrial Info reported a 35-day Pipestill 7 and East Coker turnaround from September 5, 2023, and Reuters reported the East Coker restarting on October 26, 2023.

Reuters reported the other FCC and a hydrocracker shut January 20, 2024 for a two-month overhaul, with two of four crude units planned for the third quarter of 2024; execution of that crude-unit work was not confirmed by the sources reviewed.

Source: Reuters, republished by Euronews; Industrial Info Resources; Reuters, republished by BOE Report

What ExxonMobil has said

Management named Baton Rouge among planned Gulf Coast distillate investments on October 30, 2026 without dates, and said 2027 detail would follow in late January 2027.

Source: Reuters, republished by BOE Report

What a projection means here

A projected entry is a planning estimate built from the facility's last documented turnaround and a typical unit cycle. It is not an announced schedule, and the operator has not confirmed any 2027 work at this site.

Use it to decide where to prequalify and whose next quarterly disclosure to watch. Do not use it to time mobilization or to represent a schedule to a customer.

Services to assess

These categories reflect the candidate scope. They are planning considerations, not announced work packages, contract awards or open bids.

  • Mechanical services
  • Catalyst handling
  • Inspection and NDE
  • Tower and heat-exchanger work
  • Scaffolding and insulation

Updates

Initial cycle projection from the documented 2022, 2023 and 2024 Baton Rouge turnarounds; no 2027 schedule has been disclosed.

Source: Reuters, republished by BOE Report; Industrial Info Resources; Reuters, republished by Euronews
Sources
Exxon Louisiana refinery gasoline, diesel units shut for work, sources

Reuters, republished by BOE Report · Published 2024-01-22

Today's Refining Hotline Headlines

Industrial Info Resources · Published 2023-09-06

Exxon plans to finish Baton Rouge FCC work by April 5

Reuters, republished by Euronews · Published 2022-04-01