OpenAI Stargate Milam County Data Center

OpenAI · TX

Phase
construction
Capacity
1,200 MW
Investment
Not publicly verified
Evidence confidence
98%

Last verified July 29, 2026 · 2 retained sources

Verified project facts

Project status
active
Metro area
Central Texas
Buildings
Not publicly verified
Data halls
Not publicly verified
Groundbreaking
Not publicly verified
Expected energization
Not publicly verified

Meaningful project events

Material project evidence only. Administrative database activity is excluded.

2 verified events
  1. Scale

    Project scale evidence verified

    OpenAI selected SB Energy to build and operate its 1.2 GW Milam County data-center site and states that initial facilities are under construction.

    OpenAI95% evidence confidenceOpen evidence source
  2. Project phase

    Project evidence verified

    OpenAI announced Milam County as a Stargate site to be developed with SB Energy.

    OpenAI95% evidence confidenceOpen evidence source
Source provenance

Retained evidence

How ExecGraph verifies public intelligence
OpenAI

OpenAI selected SB Energy to build and operate its 1.2 GW Milam County data-center site and states that initial facilities are under construction.

95% source confidenceofficial ownerOpen source
OpenAI

OpenAI announced Milam County as a Stargate site to be developed with SB Energy.

95% source confidenceofficial ownerOpen source