OpenAI selected SB Energy to build and operate its 1.2 GW Milam County data-center site and states that initial facilities are under construction.
construction
OpenAI Stargate Milam County Data Center
OpenAI · TX
Phase
construction
Capacity
1,200 MW
Investment
Not publicly verified
Evidence confidence
98%
Last verified October 7, 2026 · 3 retained sources
Verified project facts
Project status
active
Metro area
Central Texas
Buildings
Not publicly verified
Data halls
Not publicly verified
Groundbreaking
Not publicly verified
Expected energization
Not publicly verified
Meaningful project events
Material project evidence only. Administrative database activity is excluded.
- Scale
Project scale evidence verified
OpenAI confirms the Milam County Stargate site is 1.2 GW, with initial facilities under construction and expected to begin service during 2026.
- Scale
Project scale evidence verified
OpenAI selected SB Energy to build and operate its 1.2 GW Milam County data-center site and states that initial facilities are under construction.
- Project phase
Project evidence verified
OpenAI announced Milam County as a Stargate site to be developed with SB Energy.
Source provenance
Retained evidence
OpenAI
OpenAI
OpenAI confirms the Milam County Stargate site is 1.2 GW, with initial facilities under construction and expected to begin service during 2026.
OpenAI
OpenAI announced Milam County as a Stargate site to be developed with SB Energy.