OpenAI identifies Abilene as its flagship Stargate site and states the site is operating on Oracle Cloud Infrastructure and has trained frontier models.
operations
OpenAI Stargate I Abilene Campus
OpenAI · Abilene, TX
Phase
operations
Capacity
Not publicly verified
Investment
Not publicly verified
Evidence confidence
98%
Last verified October 7, 2026 · 3 retained sources
Verified project facts
Project status
active
Metro area
Abilene
Buildings
Not publicly verified
Data halls
Not publicly verified
Groundbreaking
Not publicly verified
Expected energization
Not publicly verified
Meaningful project events
Material project evidence only. Administrative database activity is excluded.
- Project phase
Project evidence verified
OpenAI identifies Abilene as its flagship Stargate site and states the site is operating on Oracle Cloud Infrastructure and has trained frontier models.
- Project phase
Operations status verified
OpenAI states that the Abilene flagship campus is already up and running on Oracle Cloud Infrastructure.
- Project phase
Operations status verified
OpenAI identifies Stargate I in Abilene and states that parts of the facility were up and running.
Source provenance
Retained evidence
OpenAI
OpenAI
OpenAI states that the Abilene flagship campus is already up and running on Oracle Cloud Infrastructure.
OpenAI
OpenAI identifies Stargate I in Abilene and states that parts of the facility were up and running.